Upgrading or Moving Your Electrical Meter with Bright Electric: What to Expect
By: Matt Pinkston - Master Electrician | April 23, 2024 | (Updated June 2026)

Upgrading an existing electrical service or relocating an electrical meter requires coordination between Bright Electric, CenterPoint Energy, the customer, and the local building commission.
Because the property already has electrical service, the process is a little different from installing a completely new service. CenterPoint must review and approve the project before work begins, and the actual installation requires coordination so the existing electrical service can be disconnected and restored.
To help you understand what to expect, here is the typical 7-step process.
1. Paperwork and Application Submission
Bright Electric will complete the necessary paperwork and submit the request directly to CenterPoint Energy.
We will copy you on the email so you know the request has been submitted and can follow the process from the beginning.
2. Scheduling the CenterPoint Site Visit
CenterPoint Energy will contact you directly to schedule a site visit and evaluate the proposed service upgrade or meter relocation.
Please note: CenterPoint will normally contact the customer whose name is on the electric account, not Bright Electric.
Depending on CenterPoint's current schedule, this portion of the process may take approximately 6 to 8 weeks. Unfortunately, CenterPoint's scheduling is outside Bright Electric's control.
3. CenterPoint Site Visit and Approval
A CenterPoint representative will visit the property to review the proposed work.
During the visit, they may discuss the meter location, utility connection, service route, or other requirements for the project. They will then provide approval for the project to move forward.
Once CenterPoint gives you the green light,
please notify Bright Electric immediately.
4. Permitting and Installation Scheduling
CenterPoint does not normally notify Bright Electric when the project has been approved, so we rely on you to let us know.
Once you notify us of the approval, Bright Electric will obtain the required city electrical permit and schedule the installation.
Because the existing electrical service will need to be disconnected during the work, Bright Electric will also coordinate the required service interruption with CenterPoint.
5. Completing the Electrical Upgrade
On the scheduled work day, Bright Electric will complete the electrical service upgrade or meter relocation.
During this time, electrical power to the property will be temporarily disconnected while our electricians perform the required work.
Once our portion of the installation is complete, Bright Electric will notify CenterPoint directly that the service is ready to be restored.
CenterPoint will return to the property the same day to restore electrical service.
6. City Electrical Inspection
After the electrical work has been completed, Bright Electric will request the required city electrical inspection.
The local building commission will typically perform the inspection the next business day, although the timing may vary depending on the inspector's schedule.
The inspector will review the completed installation to verify that the work meets applicable electrical codes and safety requirements.
7. Project Complete
Once the electrical upgrade has been completed and the required inspection has taken place, your service upgrade or meter relocation is complete.
Congratulations — your updated electrical service is ready for continued use.
How Long Does the Process Take?
The largest variable is usually CenterPoint's initial review and site visit.
Depending on their workload, this portion of the process may take approximately 6 to 8 weeks, so we recommend beginning the process well before you hope to have the electrical work completed.
Once the project has been approved by CenterPoint and scheduled with Bright Electric, the actual electrical upgrade is generally completed in a single day, with CenterPoint returning the same day to restore power.
Who Handles Each Part?
Bright Electric
- Completes and submits the CenterPoint paperwork
- Obtains the required electrical permit
- Coordinates the scheduled service interruption
- Completes the electrical upgrade or meter relocation
- Notifies CenterPoint when the work is ready for reconnection
- Requests the city electrical inspection
Customer
- Communicates with CenterPoint regarding the site visit
- Notifies Bright Electric once CenterPoint approves the project
CenterPoint Energy
- Reviews the proposed service change
- Performs the site visit
- Approves the project
- Disconnects or coordinates the existing utility service as required
- Restores electrical service after Bright Electric completes the work
Local Building Commission
- Performs the required electrical inspection after the installation
Planning an Electrical Service Upgrade or Meter Relocation?
Bright Electric will help guide you through each step of the process and coordinate our portion of the project with CenterPoint Energy and the local building commission.
If you're considering upgrading your electrical service or moving your electrical meter, contact Bright Electric at
(812) 401-2277.
Written & Reviewed by:
Matt Pinkston — Master Electrician (Vanderburgh County License #29714)
Operations Manager at Bright Electric
27+ years of electrical experience in Evansville and the Tri-State area.
Specializes in residential and commercial electrical work, NEC code compliance, and modern electrical safety standards.